Plan Process

Timeline
The RPGA Planning District activities are listed in chronological order.
| January 1, 2010 | RPGA Planning District formed |
| Phase 1: Background Review | June 2010 – September 2010
Research, initial community and stakeholder engagement, and completion of a Background Study. |
| September 20 2010
Curling Club Lounge – Altona, MB |
Workshop #1 |
| Phase 2: Building the Plan | September 2010 – March 2011
Undertake community and stakeholder engagement and prepare a draft Development Plan.
|
| November 29, 2010
Plum Coulee Community Hall – Plum Coulee, MB |
Workshop #2 |
| March 21, 2011
Grenta Prairie Centre – Gretna, MB |
Workshop #3 |
| Phase 3: Adopting the Plan | March 2011 – June 2011
Finalize the Development Plan and Zoning Bylaws, hold public hearings. |
| June 2011 | Public Hearing to consider by-laws. |
| Sept 2011 | Provincial Approval Process |